How This Quiz Works

  • Pick an answer and press Check my answer. You see at once whether you were right, and why.
  • At the end you get your score and the topics to work on. Nothing is hidden behind a sign-up.
  • You can use it with a keyboard: Tab to the answers, arrow keys to choose, Enter to check.
  • These are practice questions written by The Online Crane School for our own course. They are not questions from the real exam, and a practice score does not predict an exam result.

Lattice Boom Crane Practice Questions

Written to the outline of the CCO Mobile Crane Operator Lattice Boom Crane (LAT) specialty written exam (NCCCO). Topics covered: Site, Operations, Technical Knowledge, Core Review, Load Charts.

  1. Question 1 of 10 Site The only laydown area for a 180 ft boom runs under an energized 13.8 kV distribution line that hangs 45 ft above the ground. May the boom be assembled there?
    Show the answer and why

    Answer: D. No, unless the line is de-energized and visibly grounded

    OSHA 1926.1407(c) prohibits any part of a crane, load line or load, whether partially or fully assembled, from being below a power line unless the employer has confirmed that the utility owner/operator has de-energized the line and visibly grounded it at the worksite. Clearance and spotters do not change that.

  2. Question 2 of 10 Operations The wind at the boom tip rises from 15 mph to 30 mph. About how many times greater is the force of the wind on the boom and load?
    Show the answer and why

    Answer: B. 4 times

    Wind force rises with the square of the wind speed. Doubling the speed from 15 to 30 mph multiplies the force by 2 × 2 = 4. That is why a small rise in wind speed uses up the crane's margin quickly.

  3. Question 3 of 10 Technical Knowledge Compared with a telescopic boom, how does a lattice boom carry its load?
    Show the answer and why

    Answer: A. Mainly in compression, hung from its tip

    A lattice boom is supported at its tip by the pendants, so the boom is squeezed end to end in compression. A telescopic boom is propped by a lift cylinder and carries load by bending. This is why a lattice boom is lighter for its length and why buckling and side load are its main weaknesses.

  4. Question 4 of 10 Core Review A telescopic crane’s chart instructs users to take the smaller of adjacent ratings for intermediate boom lengths. The boom length falls between two columns. Which capacity applies?
    Show the answer and why

    Answer: D. The lower of the two capacities

    Use the chart’s stated rule for intermediate lengths. Other charts can specify different rules for intermediate values. The shorter boom is not always the lower number, so compare the two values.

  5. Question 5 of 10 Load Charts For an LC-150 chart exercise, a load is positioned at a 60 ft radius before its weight comes onto the crane. The boom deflects outward as it takes the load. Which radius must the lift plan cover?
    Show the answer and why

    Answer: A. The longest loaded radius anywhere on the planned path

    The chart rates the radius under load. Allow for deflection and verify capacity at the longest loaded radius throughout the planned movement. A pre-lift tape measurement alone does not establish that capacity.

  6. Question 6 of 10 Site Who must supervise an operation in which a crane travels with a load, under OSHA 1926.1417(u)?
    Show the answer and why

    Answer: C. A competent person

    A competent person must supervise travel with a load, determine whether rated capacity must be reduced, and make determinations on load position, boom location, ground support, travel route, overhead obstructions and speed. Travel with a load is prohibited if the manufacturer prohibits it.

  7. Question 7 of 10 Operations A lattice crane is booming down to reach a landing spot with a load on the whip line. The ball is already close to the jib tip. What must the operator do as the boom comes down?
    Show the answer and why

    Answer: A. Pay out load line to keep the ball clear

    Lowering a lattice boom takes up load line and draws the ball toward the tip. Unless line is paid out, the ball two-blocks, and a single-part whip line gets there quickly. The anti two-block device is a backup, not a substitute for watching the ball.

  8. Question 8 of 10 Technical Knowledge A main hoist rope that is not rotation-resistant has three broken wires in one strand, all within one rope lay. What is required?
    Show the answer and why

    Answer: B. Stop use pending the Category II disposition under OSHA

    Three broken wires in one strand in one lay of this running rope are a Category II deficiency under 1926.1413(a)(2)(ii). Stop operations involving the rope until the employer meets (a)(4)(ii) by following the manufacturer's removal criterion or written criterion for that rope, replacing it, or correcting a localized deficiency by permitted shortening with two wraps remaining at the lowest position.

  9. Question 9 of 10 Core Review In what order must the three elements of a voice signal be given?
    Show the answer and why

    Answer: C. Function and direction; distance or speed; function and stop

    OSHA 1926.1421(b) requires each voice signal to contain, in order: the function and direction, the distance and/or speed, and the function and stop command. For example: "swing right, ten feet, five feet, swing stop".

  10. Question 10 of 10 Load Charts The LC-150 is working with its crawlers retracted and 120 ft of main boom. For one light pick, the crew wants to add the 30 ft jib. What does the chart rate for a lift on the jib in this setup?
    Show the answer and why

    Answer: D. Nothing: no jib lifts are rated with the crawlers retracted

    Retracting the crawlers needs its own chart. Chart C stops at 140 ft of boom, and no jib lifts are rated with the crawlers retracted. A setup the chart does not name has no rating, however light the load. Lesson: Range diagrams, work areas and crawler position.

More Free Practice

Free Lattice Boom Crane sample lesson

Read one full lesson: The lattice boom: chords, lacings and sections.

All free practice quizzes

Ten questions and a sample lesson for each course.